More interior photos update. Most of the lower levels units are now fitted with doors and were locked, presumably all internal finishes had been completed. Only the higher levels units are accessible. Sanitary wares and fittings has been fitted into the bathrooms in the mock up unit, as shown: -
Bathroom 2
Inno brand sink, didn't like the plug that is attached with a chain, would love the pop up type. Ah! Well...
Inno brand WC, well at least it's a push button type. Certainly hope that the bip tap would come with a hose & spray bidet
Ceiling done to Bathroom 1, the compartment for pipes on the left had actually mad the shower compartment a bit small. Dunno why they use this type of ceiling, looks like office ;)
Ceiling done to Bathroom 2, this bathroom is actually bigger than Bathroom 1, sigh...
For those who bought some of those top most floor units, the Living area is much higher, I would say about 14 to 15 feet height. Very Grand
Same with the Dining area. The down side, I suppose is that you need more energy in terms of air conditioning to cool the space :)
Tower 2 is coming up fast, At this rate, lets hope that the apartment can be handed over earlier : )
Structural Works For Southern Wing Of Tower 2 Is Completed Up To The Roof Already
Northern Wing Of Tower 2 Still Has 4 Levels To Go Before Reaching The Roof
View Of Tower 2 Staircase Taken from Tower 1 Staircase, This Is The Little Gap Between The Two Towers. The Gap Is Very Close Compared To What Is Shown In The Artist Impression
Site progress photos taken this afternoon. Works are now concentrated on Tower 2 with finishing works being done for Tower 1. This project will be very prominent in BK once completed :)
Tower 1, Still Finishing Off The Top Most Units Of Northern Wing
Tower 1, Southern Wing Not Much Activities At The Moment, I Suppose They Are Waiting For Tower 2 To Come Up Before Continuing With The Painting
Tower 2, Southern Wing Structural Works For 7th Floor Commenced, Brick Works Up To 3rd Floor
Tower 2, Northern Wing Structural Works Up To 6th Floor, Brick Works Up To 3rd Floor
Tower 2, At The Rate They Are Going, Let's Hope They Can Complete All Structural Works By The End Of This Year
Seems that all works are concentrated on Tower 2, which is a good thing as the handover date is the same. At least there won't be anymore progress claim for Tower 1 until they do the sewerage, road and drainage works.
Tower 1, They Are Finishing Off The Top Most Units And The Roof For Lift Lobby
Tower 1, I Noticed That They Are Using 3 Different Colours For The External Walls At The Living Areas, Looks Rather Funny I Think
Tower 2, Construction Works Catching Up Fast!
Tower 2, Structure Up To 5th Floor And Followed By Brick Walls And Window Frames At 1st Floor
View Of Both Towers From Taman Puncak Kinrara At The Back
Works on site is progressing well, actually I hope it could be faster. Well at least Tower 2 is coming up. More exciting times ahead for Tower 2 purchasers...
Tower 2 coming up, one more floor and the northern wing of Tower 1 will be covered.
Tower 1, southern wing not much activities except the glass panels for unit A01-09 had been installed.
The topping up of Tower 1, well not really, still have the roof slab for those units at Level 11 to go.
Tower 2 southern wing up to third floor now :)
Tower 2 northern wing also catching up with its southern wing.