Wednesday, September 19, 2007

Site Photos September 2007

Its been a while since I last updated my blog on the progress of works, as works have been extremely slooooooooooow on site. Its one year already that they have wasted! Imagine we could have gotten our apartment 1 year earlier if they had started works at the end of last year. Now let's hope that they can complete the projects in the next 2 years.
17 September 2007; 1st floor beam formworks for Tower 1 can be seen.


17 September 2007; columns on ground floor of Tower A coming up.

By the way, there is still no name of the main contractor on the project signboard!



Tuesday, August 21, 2007

Around BK: Giant Hypermarket

The Giant Hypermarket in Bandar Kinrara, BK 5A has finally been completed and the grand opening is tomorrow, 23-08-2007. It will definitely increase the value of SR upon completion . . . . . . . . . . if it ever gets completed at all, as works on site is rather stagnent :(

Wednesday, July 4, 2007

Site Photos 02 July 2007

Temporary Hoardings and Site Office up but still not much construction activities on site. Probably transition period as the piling contractor had completed the works and now waiting for the Main Contractor to come in ?




Thursday, June 21, 2007

Construction Works to go Full Swing?

There seems to be more activities on site recently. Hopefully signs that they are proceeding full swing with the construction works after completing piling works. The site is now in the process of being hoarded. However still no name on the signboard who the Main Contractor is. Do you think Pembinaan Sierra Mal will contruct the building themselves?

Temporary Hoardings Are Being Done On Site



There are also some temporary kongsi and containers being placed at the SR 2 site. I think they would be housing their workers for SR 1 there. So I don't think they would launch SR 2 this year.

Kongsi House at SR 2 Site
Containers at SR 2 site

Tuesday, June 19, 2007

Site Photos 17 June 2007

Was at the site on Sunday, there seems to be some sort of activities at the Tower 2 area as shown in the photos. I thought they are beginning to cast the floor slab and was wondering why they didn't start with Tower 1. However, a friend of mine told me that they are preparing to do a test pile.



Tuesday, June 12, 2007

Site Photos 11 June 2007

Took the following site photos yesterday. There seems to be not much activities on site recently.
May be they are concentrating on the piling works for Tower 2, so as to be able to bill the purchasers. Even the steel exposed steel bars for the piles in Tower 1 are starting to rust. Should this be a concern?


Tower 1

Tower 2
Construction access

Wednesday, May 23, 2007

Site Photos 19 May 2007

Not much activities on site over the past few weeks. I think the contractor is rushing to complete the piling works for Tower 2 so that the developer can bill the purchasers of that tower as well.






Thought I noticed some earth movements at the slope next to Tower A! You people be the judge. Isn't the contractor suppose to provide some sort of slope protection upon cutting the slope?