Pass by the site today and snap a few photos in a rush. Buildings works are almost ready, however Tower 2 is still far behind as glazing have yet to be installed for the windows. Now they are concentrated on the external works
I wonder if fellow Tower 2 Serrians have a later Sale and Purchase Agreement (SPA) date compare to those in Tower 1. My last date for Vacant Possession is 20 December 2009!
Looks like we will be exercising Clause 26 of the SPA and claim Liquidated Damages from the developer.
Also noticed a new signboard on site put up by the developer's agent selling and renting out units.
View of Tower 1
View of Tower 2, Window Glazing Yet To Be Installed
With Both Towers Almost Completed, Works Are Now Concentrated At The Recreational Areas
A small commotion occurred on the Sierra Residency construction site yesterday: -
Friday October 9, 2009
Landslip at Kinrara construction site
By JADE CHAN
A LANDSLIP occurred along Jalan BK 4/10C in Bandar Kinrara 4, Puchong, yesterday morning but therer was no major damage.
Kinrara assemblyman Teresa Kok and her team visited the site shortly after receiving news about the incident to assess the situation.
According to Kok’s assistant and former Subang Jaya Municipal councillor Gary Chong, the landslip occurred at a construction site of some medium-cost condominium blocks, which is near some single-storey houses.
“The developer, who was excavating the drain, had dumped the soil next to some hoarding. The hoarding eventually gave way.
Minor mishap: The landslip caused earth from the construction site (left) to break the hoarding and spill over onto the lawn of a neighbouring single-storey house.
“There was some minor damage, like a collapsed gantry and damaged drain, not to mention a road and drains that are soiled with mud,” he said.
“It so happened that the incident happened in the morning when most residents were at work. Their vehicles could’ve been damaged had the landslip occurred much later.”
Chong said the Subang Jaya Municipal Council’s (MPSJ) Engineering Department had sent a team to the site and instructed the developer to rectify the situation immediately.
“The MPSJ has given the developer one day to complete the rectification work or be slapped with a summons.
“The developer has agreed to undertake the repair work,” he said.
Tower 2 Southern Wing: Those Jokers Tried To Paint The External Wall From The Master Bedroom Window. Now Let's Wait & See How They Finish The Painting The Wall
Tower 2 View From East. Painting In Progress
Tower 2: Construction Of The Lower Ground Car Park Can Be Seen
I was at MPSJ this morning and noticed that Prasarana had set up a booth to display the proposed extension and alignment of the two LRT lines, one of which would pass through Bandar Kinrara. There will be 3 proposed stations at Bandar Kinrara, at BK 2 / BK5A, at BK3 / Taman Perindustrian Kinrara and at BK9 / Taman Industri Bukit Kinrara. This is very good news indeed.
The booth will be there for 3 months until 14 December 2009 for public viewing and comments. The following were photos taken at the booth: -
The Futuristic Design Of The Proposed LRT Stations.
Passed by the site over the weekend and manage to snap the following photo from outside. I think they have started constructing the Swimming Pool :) Will try to get more photos this week: -