Tuesday, June 12, 2007

Site Photos 11 June 2007

Took the following site photos yesterday. There seems to be not much activities on site recently.
May be they are concentrating on the piling works for Tower 2, so as to be able to bill the purchasers. Even the steel exposed steel bars for the piles in Tower 1 are starting to rust. Should this be a concern?


Tower 1

Tower 2
Construction access

2 comments:

Anonymous said...

i bought a unit in tower2. already got the progress claim from the developer in end May. so they should be starting other works other than the piling already. frankly, i am a bit worried. wonde rif there's way to stop the bank from releasing hte loan....
- kl

Anonymous said...

The bank will release the loan based on the architect's certification. If they don't, the developer would charge you interest at 10% p.a. per day on the amount due after 21 days from the date of their invoice.

I think your only recourse is that, if you feel that the works had been wrongly / prematurely certified by the architects, you can complaint to the Board of Architects.