Bandar Kinrara

Artist Impression

Swimming Pool & Wading Pool

Scaled Model

Site Plan

Tuesday, March 25, 2008

Site Photos 25 March 2008

More progress site photos . They have commenced external plastering works for the southern wing of Tower 1, for those units facing the pool/playground. So owners of those units prepare to pay more interest as the bank will be releasing the next 10% very soon!
Tower 1, External Plastering Works Commenced

Tower 1

Tower 1

Tower 1, I noticed that they have made some changes to the external walls for the right hand section of this facade. If you look at the photos of the Artist Impression & Scaled Model, there were white fins/hood for all units No. 12. I felt that by doing that they had compromise the look of the building, not to mention cheaper and easier for them to construct.

Tower 2, southern wing 1st floor slab casted.

1 comment:

Anonymous said...

i am planning to let go of my unit..
If anyone is interested kindly contact me...
Deric 016 Four781282..