Thursday, March 26, 2009

Photos Of The Common Areas

Works are concentrated in the apartments units, tiling works plus installation of sanitary wares. Tiling works are now progressing for the upper floor units of Tower 1, Here are some progress photos of the common areas: -

Tower 1 Lift Lobby, Lift Door Is on the Left & On The Right Services Compartments

Tower 1 Southern Wing Corridor

Tower 1 Northern Wing Corridor

Car Park Areas At The Ground Floor Of Tower 1

More Car Park Areas At The Ground Floor Of Tower 1

2 comments:

Anonymous said...

no workers seen in the pictures

Anonymous said...

do u guys think our project ni on the track? rasa macam slow jer...