Few areas that raised my concern :-

end April 2010, we were being verbally informed by the developer that CF was ready, thus we can start the renovation work immediately.

today 11May2010, i was heading to the management office to claim for the alarm system. However, i was been told that CF actually not ready. We are being cheated!!

is this the reason why there's still no electricity / water supply?
what is the purpose of handling keys to us?
why should we pay for the maintenance fees?

Pitiful to a malay owner who has moved in to his unit at Block B, which he and his pregnant wife and little kid has to stay in a home without electricity & water supply.

After this scene, i heading to the developer office located at Taman Bukit Kinrara to find for fact.

The office light was "ON" when i reached there, however there is no answer from the office no matter how long i knock the gate. thus, i tried to call in the general line, and the mobile # of the Project Manager of Sierramal, nobody taking up the call also. when i look-up again, the light was "OFF" already. WHAT'S HAPPENED?? Why are they hiding??

I sincerely hope all owners start to action now, pls share your thought how should we do next.

Below is the address & contact of the developer :-

No. 19-1, Jalan TBK 1/6, Taman Bukit Kinrara
Tel : 03-8076 8525
Mobile : 012-684 6763
Project Manager : Wan (019-655 9171)

Understand the developer will be launching the Sierra 2 in July 2010.
i'm very sure they will never can get through if our issue remain unsolved.