Monday, December 10, 2007

Site Photos 08 December 2007

Looks like Units 01 to 04 & 10 to 15 of Tower 1 have reached 4th Floor. Any one out there of these units and floors receive the progress billing from the developer yet? Units 05 to 09 are also catching up.

I also noticed that they had commenced works on ground beams for Tower 2. So, it should be coming up very soon.




Wednesday, November 28, 2007

Site Photos 27 November 2007

Twenty days later from the last update, they have reached 3rd floor (Level 4). As Max commented, it is only the front portion of Tower 1. The works at the back portion of Tower 1 is still catching up at 1st/2nd floor.

View From Jalan BK 5B


Front Portion Of Tower 1

Back Portion Of Tower 1

Back Portion of Tower 1
As for Tower 2, you guys & gals have to be more patience ;)

Wednesday, November 14, 2007

Site Photos 7 November 2007

Exciting times are here! It is so good to see progress on site... lets hope that they will keep it up.

Second floor coming up. I wonder if they have billed those purchasers on the First floor.


The other wing of Tower 1 also can be seen coming up


Wednesday, October 31, 2007

Site Photos 25 October 2007

More site progress site photos taken on 25 October 2007, They are getting ready to cast the 2nd floor slab. It seems rather fast that they take out the form works for the shear walls at 1st floor.


Monday, October 22, 2007

Site Photos 19 October 2007

More progress site photos taken on 19 October 2007: -

View from Jalan BK 5B at Unit A01-12 & Unit A01-13 of Tower 1
It is confirm that they are using shear walls system for the apartment units

Tower 1 First Floor apartments' shear walls coming up

This is the first time I see so many workers on site :)

Ground Floor car park for Tower 1

Wednesday, September 19, 2007

Site Photos September 2007

Its been a while since I last updated my blog on the progress of works, as works have been extremely slooooooooooow on site. Its one year already that they have wasted! Imagine we could have gotten our apartment 1 year earlier if they had started works at the end of last year. Now let's hope that they can complete the projects in the next 2 years.
17 September 2007; 1st floor beam formworks for Tower 1 can be seen.


17 September 2007; columns on ground floor of Tower A coming up.

By the way, there is still no name of the main contractor on the project signboard!



Tuesday, August 21, 2007

Around BK: Giant Hypermarket

The Giant Hypermarket in Bandar Kinrara, BK 5A has finally been completed and the grand opening is tomorrow, 23-08-2007. It will definitely increase the value of SR upon completion . . . . . . . . . . if it ever gets completed at all, as works on site is rather stagnent :(