Bandar Kinrara

Artist Impression

Swimming Pool & Wading Pool

Scaled Model

Site Plan

Saturday, April 28, 2007

Site Photos 25 April 2007

25042007

25042007

Wednesday, April 25, 2007

Around BK: Kinrara Cricket Academy

Kinrara Cricket Academy is located along Jalan BK 5. However, the entrance is actually located along Jalan BK 5A/1. The oval itself is actually very well maintained. Too bad cricket is not very popular in Malaysia.

Kinrara Cricket Oval had recently hosted international cricket matches

Monday, April 23, 2007

LRT at Bandar Kinrara

Since the government made the anouncement that LRT would be extended from Sri Petaling to Puchong back in August 2006, there had been many discussions over this issue. I came accross the the latest article in The Star last Friday, 20th April 2007 at the following link: -

http://www.thestar.com.my/news/story.asp?file=/2007/4/20/parliament/17497457&sec=parliament

Let's hope that they can definitely start work on the LRT next year and complete on schedule in 2010, at the same time SR is ready! :)


Thursday, April 19, 2007

Progress Payment Stage 2a

Received a progress payment notice from the developer yesterday for Tower 1 with the following Architect's certificate attached. Invoice is dated 13.04.2007 and payment due date is 09.05.2007.

It says completion of piling and foundation of the building. I think piling is completed from what I have seen on site, but what about the foundation bit? Is there anything more to it? What about pilecaps, raft slab, footing and stumps that must be completed as listed in the circular in the Board of Architects website?


The following photos were taken on 19042007, seven days after the Architect certify the completion of the piling and foundation.

Monday, April 16, 2007

Around BK: Kinrara Golf Club

Kinrara Golf Club is located along Jalan BK 6 in Bandar Kinrara. Its 18-hole golf course will presents challenges to golf enthusiast moving into SR, since it is only a stone throw away.

For those who are not into golf, like me, Kinrara Golf Club also provides a variety of family oriented facilities ranging from tennis, swimming pool, gymnasium / aerobic room and others.





Friday, April 13, 2007

Site Photos 10 April 2007

Photo Taken From Taman Perindustrian Kinrara Near The Surau, Looks Like They Have Filled Up Part Of The Land Behind The Project As Well.



Piling Works Completed But No Signs Of Footing Works, I Was Told That They Need To Complete The Footings Works As The Whole Foundation System Before Sending Out Their Progress Billings


Tuesday, April 10, 2007

Stage Billings By Developer

I came accross the following link in the website of the Board Of Architects Malaysia which may be helpful to everyone. At least we know what need and need not to be completed when the developer send the bill to us/our end financier for payment. You have to scroll to Page 9, Schedule H which is applicable for sub-divided building.

http://www.lam.gov.my/download/4-2003(BI).pdf

For the next stage, all foundation works below the lowest floor slab (ie. the car park floor) must be completed including pile caps. Currently, I think they have only completed the piling for Tower 1, I think they still need to do the pile caps before sending out the bill.

Site Photos 5 April 2007

Piling works continuing at Tower 2 area
05042007


05042007

05042007

Wednesday, April 4, 2007

Site Photo 2 April 2007

02042007 , Additional Building Materials Were Seen On
Site Covered In Blue Plastic, Not Sure What It Is Though

Tuesday, April 3, 2007

Sierra Residency II

Got the following layout regarding the other project by Pembinaan Sierra Mal Sdn Bhd in the vicinity along Jalan BK 5B /5. The Planning approval was dated back in 2 August 2005. Was told by the developer's representative that they are changing the layout due to complications of incorporating the drain reserved within the project.