Thursday, April 19, 2007

Progress Payment Stage 2a

Received a progress payment notice from the developer yesterday for Tower 1 with the following Architect's certificate attached. Invoice is dated 13.04.2007 and payment due date is 09.05.2007.

It says completion of piling and foundation of the building. I think piling is completed from what I have seen on site, but what about the foundation bit? Is there anything more to it? What about pilecaps, raft slab, footing and stumps that must be completed as listed in the circular in the Board of Architects website?


The following photos were taken on 19042007, seven days after the Architect certify the completion of the piling and foundation.

5 comments:

Anonymous said...

hi.
the architect cannot issue the ceritifcate if the foundation work is not completed... you can wrtie to the developer to enquire about this.

Anonymous said...

Passion > Thanks Cel for the update!

Cel said...

I have made an inquiry with the people in the National House Buyers Association and were asked to inquire with the Board of Architects Malaysia.

I will do so and keep everyone posted on this issue.

Anonymous said...

I bought a unit in block A but haven't received the billing...

Cel said...

Hi Heskey,
How can that be! I am sure your unit would be listed in the architect's cert as well. This is rather weird...